Saturday 30 March 2013

Almost at Lockup

So it has been a month since I have posted anything but a lot has been happening in that time.

27 February 2013 - The majority of our brickwork had been completed (except for the window sills and the top of the 2 pillars at the front.

By the 11th of March we had our gutters and fascias done and half our roof was on.

On 15 March 2013 the entire roof was up and the Brickwork was pretty much completed.

On 20 March 2013 our electrician completed the electrical rough in and we did a walk through with our SS on 21 March 2013.  We had an independent inspection done and only a few minor things were found.

On 25 March 2013 our Bricks were cleaned and the scaffolding was taken down.  The minor items pointed out by our independent inspection were fixed.  We have some of the panels above the pillars done but I think there is more to come.

On 27 March 2013 our wall installation had been done and gyprock had been started.

We are really happy with our new brick colour now that the bricks have been cleaned!  It is really great to see the colours you pick in the colour appointment come to life.

27 February 2013

11 March 2013 - Half a Roof

WALK THROUGH WITH OUR SS - 21 March 2013



Outlook from the Master Bedroom

Home Theatre windows (I really love these)

Shower recess in the ensuite



TV alcove in the main living area

Alfresco

Slab for the Water Tank
BRICKS AFTER BEING CLEANED - 25 March 2013